Case status: Closed at the fortieth meeting of the Compliance Committee held from 25 to 28 March 2013 (see para. 20 of the Report of the Committee's fortieth meeting).
Follow-up: -
Topics: Public participation.
Articles alleged: 6 (3); 7.
Articles considered by the Committee: -
Articles, if any, found in non-compliance: -
Summary: The communication was submitted to the Compliance Committee on 23 February 2012, by the Danish Agriculture and Food Council, represented by Mr. Hakun Djurhuus, alleging non-compliance by Denmark with the public participation provisions of the Convention in relation to the adoption of the Danish River Management Plans, under the EU Water Framework Directive.
Document | Status | Date received or posted by the secretariat |
---|---|---|
Datasheet ACCC/C/2012/67 | Latest datasheet on the status of the communication | 14.05.2013 |
Determination on admissibility | At CC-36 | 30.03.2012 |
Communication | From the communicant | 23.02.2012 |
Annex 1 Consultation responses to the draft river basin management plans (Dk) (En) Annex 2 Guidance regarding supplementary consultation (Dk) (En)
|
From the communicant | 23.02.2012 |
Letters to the Party concerned, the communicant and questions from the Committee | From the secretariat | 08.05.2012 |
Annex 1. Excerpt from the Consolidated Law on |
From the communicant | 21.09.2012 |
Motion for suspension of the case | From the Party concerned | 08.10.2012 |
Correspondence regarding the extension of the deadline for the Party concerned to respond | From the secretariat | 12.10.2012 |
Request for further extension of the deadline to respond | From the Party | 09.11.2012 |
Response concerning the extension/suspension |
From the communicant | 27.11.2012 |
Letter and Annex (decision of the Nature and Environmental Board of Appeal in Dk) | From the Party concerned | 10.12.2012 |
Letter | From the communicant | 20.12.2012 |
Letter to parties after CC-39 | From the secretariat | 14.01.2013 |
Letter on suspension of the case | From the communicant | 06.02.2013 |
Letter to close the case Annex (decision of the Environmental Board of Appeal) |
From the Party concerned | 08.02.2013 |
Letter to parties | From the secretariat | 22.04.2013 |