ECE.MP.WH.CC.CI.1 Portugal
Portugal failed to submit its summary report within the second reporting exercise
Document | Status | Date received or posted by the secretariat | |
---|---|---|---|
Letter to the Party informing about the decision to initiate the case | By the secretariat | 19 December 2014 | |
Draft findings and recommendations | By the Committee | 20 April 2015 | |
Letter to the Party informing about the draft findings and recommendations | By the secretariat | 20 April 2015 | |
Findings and recommendations (advance unedited version) | By the Committee | 15 July 2015 | |
Letter to the Party informing about the findings and recommendations as adopted | By the secretariat | 18 September 2015 | |
Findings and recommendations with regard to case ECE/MP.WH/CC/CI/1 initiated by the Committee concerning compliance by Portugal (Adopted by the Compliance Committee on 15 July 2015) | By the Committee | 25 January 2016 |