SEARCH   SITE MAP
UNUnited Nations Economic Commission for Europe

Protocol on Strategic Environmental Assessment (SEA)

Implementation of Directive 2001/42 on the Assessment of the Effects of Certain Plans and Programmes on the Environment (the 'EC Guide')


4. GENERAL OBLIGATIONS

Table of Contents

6. QUALITY OF THE ENVIRONMENTAL REPORT

5. THE ENVIRONMENTAL REPORT

5.1. The environmental report is the central part of the environmental assessment required by the Directive. It also forms the main basis for monitoring the significant effects of the implementation of the plan or programme.

5.2. The environmental report is an important tool for integrating environmental considerations into the preparation and adoption of plans and programmes since it ensures that their likely significant effects on the environment are identified, described and assessed and taken into account in that process. The preparation of the environmental report and the integration of the environmental considerations into the preparation of plans and programmes form an iterative process that should contribute to more sustainable solutions in decision-making.

5.3. The provisions on the environmental report are mainly expressed in Article 2 (Definitions), Article 5 (Environmental Report) and Annex I. In addition, the environmental report must be subject to consultation as provided for in Articles 6 and 7; it must be taken into account during the preparation of the plan or programme (Article 8) and, when the plan or programme is adopted, information must be made available on how this was done (Article 9); and it must be of sufficient quality to meet the requirements of the Directive (Article 12).

Article 2(c)

For the purposes of this Directive: ..

(c) 'environmental report' shall mean the part of the plan or programme documentation containing the information required in Article 5 and Annex I.

5.4. Article 2(c) defines the environmental report as a part of the plan or programme documentation with a specified content. This implies that the environmental report should be a coherent text or texts. Although this is not required by the Directive, it maybe helpful to structure the report, so far as possible, on the headings used in Annex I. The Directive does not specify whether the report should be integrated in the plan or programme itself or a separate document. If it is integrated it should be clearly distinguishable as a separate part of the plan or programme, and be easy to find and assimilate for the public and authorities. In any case, there must always be a non-technical summary of the information provided under the headings listed in Annex I.

5.5. The environmental report might in many cases be a part of a wider assessment of the plan or programme. It could, for example, be part of a document on sustainability assessment covering also social and economic effects, or a sustainability assessment could be integrated in the plan or programme. Either model would be an acceptable way of complying with the Directive provided it fully met the requirements of the Directive.

Article 5(1)

Where an environmental assessment is required under Article 3(1), an environmental report shall be prepared in which the likely significant effects on the environment of implementing the plan or programme, and reasonable alternatives taking into account the objectives and the geographical scope of the plan or programme, are identified, described and evaluated. The information to be given for this purpose is referred to in Annex I.

5.6. Article 5(1) gives the basic requirements for the environmental report. The tasks of the report are to identify, describe and evaluate the likely significant effects on the environment of the plan or programme and its reasonable alternatives. Annex I gives further provisions on which information must be provided concerning these effects. The studying of alternatives is an important element of the assessment and the Directive calls for a more comprehensive assessment of them than does the EIA Directive. Alternatives are discussed in paragraphs 5.11 - 5.14 below.

5.7. According to Article 4(1) the environmental assessment shall be carried out during the preparation of a plan or programme and before its adoption or submission to the legislative procedure. The process of preparing the report should start as early as possible and, ideally, at the same time as the preparation of the plan or programme. The preparation of the report should normally have ended when the report is made available to authorities and the public in accordance with Article 6(1).

5.8. Article 5(1) does not explicitly state who is responsible for preparing the environmental report but it would in many cases be the authority or natural or legal person responsible for preparing the plan or programme.

5.9. What is meant by the implementation of a plan or programme cannot be defined unambiguously. It depends to a large extent on the character of the plan or programme. For plans or programmes that fall within the scope of the Directive because of the condition in Article 3(2)(a) (setting the framework for projects in various sectors) and Article 3(4) (other plans and programmes setting the framework for projects), implementation could mean among other things the implementation of projects that correspond to such a framework. However, since there might be several ways of fulfilling the requirements of such a framework, implementation of the plan or programme cannot generally be reduced to the implementation of specific single projects. In any case, a plan or programme may include elements that are not project-related but are important to its success. The effects of those aspects of the implementation should also form part of the assessment. For the plans and programmes that fall within the scope because of the condition in Article 3(2)(b) (require an assessment pursuant to Article 6 or 7 of Directive 92/43/EEC), the implementation may be conceived in the light of Article 6(3) of the Habitats Directive which calls for an assessment of the implications for a site in view of the site's conservation objectives see also paragraph 3.33 above).

5.10. Implementation of a plan or programme could cover a wide array of issues and provisions and it should be noted that an assessment has to focus on the part of implementation that is likely to have significant environmental effects. All parts of the implementation should be studied, however, as taken together they might have significant effects. Whether implementation of different parts of the plan or programme actually will take place is not a matter for the assessment to consider.

Alternatives

5.11. The obligation to identify, describe and evaluate reasonable alternatives must be read in the context of the objective of the Directive which is to ensure that the effects of implementing plans and programmes are taken into account during their preparation and before their adoption.

5.12. In requiring the likely significant environmental effects of reasonable alternatives to be identified, described and evaluated, the Directive makes no distinction between the assessment requirements for the drafted plan or programme and for the alternatives.[14] The essential thing is that the likely significant effects of the plan or programme and the alternatives are identified, described and evaluated in a comparable way. The requirements in Article 5(2) concerning scope and level of detail for the information in the report apply to the assessment of alternatives as well. It is essential that the authority or parliament responsible for the adoption of the plan or programme as well as the authorities and the public consulted, are presented with an accurate picture of what reasonable alternatives there are and why they not are considered to be the best option. The information referred to in Annex I should thus be provided for the alternatives chosen. This includes for example the information for Annex I (b) on the likely evolution of the current state of the environment without the implementation of the alternative. That evolution could be another one than that related to the plan or programme in cases when it concerns different areas or aspects.

5.13. The text of the Directive does not say what is meant by a reasonable alternative to a plan or programme. The first consideration in deciding on possible reasonable alternatives should be to take into account the objectives and the geographical scope of the plan or programme. The text does not specify whether alternative plans or programmes are meant, or different alternatives within a plan or programme. In practice, different alternatives within a plan will usually be assessed (e.g. different means of waste disposal within a waste management plan, or different ways of developing an area within a land use plan). An alternative can thus be a different way of fulfilling the objectives of the plan or programme. For land use plans, or town and country planning plans, obvious alternatives are different uses of areas designated for specific activities or purposes, and alternative areas for such activities. For plans or programmes covering long time frames, especially those covering the very distant future, alternative scenario development is a way of exploring alternatives and their effects. As an example, the Regional Development Plans for the county of Stockholm have for a long time been elaborated on such a scenario model.

5.14. The alternatives chosen should be realistic. Part of the reason for studying alternatives, is to find ways of reducing or avoiding the significant adverse environmental effects of the proposed plan or programme. Ideally, though the Directive does not require that, the final draft plan or programme would be the one which best contributes to the objectives set out in Article 1. A deliberate selection of alternatives for assessment, which had much more adverse effects, in order to promote the draft plan or programme would not be appropriate for the fulfilment of the purpose of this paragraph. To be genuine, alternatives must also fall within the legal and geographical competence of the authority concerned. An outline of the reasons for selecting the alternatives dealt with is required by Annex I (h).

Articles 5(2) and 5(3)

2. The environmental report prepared pursuant to paragraph 1 shall include the information that may reasonably be required taking into account current knowledge and methods of assessment, the contents and level of detail in the plan or programme, its stage in the decision-making process and the extent to which certain matters are more appropriately assessed at different levels in that process in order to avoid duplication of the assessment.

3. Relevant information available on environmental effects of the plans and programmes and obtained at other levels of decision-making or through other Community legislation may be used for providing the information referred to in Annex I.

5.15. The starting point for the interpretation of these paragraphs is the requirement to provide information on the likely significant effects on the environment of the plan or programme. This information must be provided insofar as it may reasonably be required taking into account the factors mentioned in paragraph 2.

5.16. The reference to 'contents and level of detail in the plan or programme' is a recognition that, in the environmental report for a broad-brush plan or programme, very detailed information and analysis may not be necessary, (for example, a plan or programme at the top of a hierarchy which descends from the general to the particular); whereas much more detail would be expected for a plan or programme that itself contained a higher level of detail. So the environmental report for a national plan might not need to assess the effects of the plan on, say, every river in the country; but the environmental report underpinning a town plan would certainly be expected to address its implications for rivers or other waterbodies in or near the town.

5.17. Article 5(3) emphasizes the desirability of rationalising the collection and production of information; it provides that relevant information (which might include analysis as well as data) already available from other sources may be used in compiling the environmental report. The value of this is obvious when plans and programmes form part of a hierarchy and for those cases Article 4(3) refers to the application of Article 5(2) and 5(3), especially for the purpose of avoiding duplication of the assessment. This issue is covered in paragraphs 4.5 - 4.7 above. Information obtained in other decision-making system, such as plans or programmes in other sectors, or from implementing other Community legislation such as the Water Framework Directive (2000/60/EC) can likewise be used.

Article 5(4)

The authorities referred to in Article 6(3) shall be consulted when deciding on the scope and level of detail of the information which must be included in the environmental report

5.18. The relevant environmental authorities, designated under Article 6(3), must be consulted when a decision is taken on the scope and level of detail of the information to be included in the environmental report. Those authorities might also be engaged in the preparation of the report throughout the process of preparing and adopting the plan or programme. Further information is to be found in section 7 below on consultation.

Annex I

5.19 Annex I specifies the information that is to be provided in the environmental report. The ten paragraphs of the Annex set out a broad spectrum of issues to be dealt with, each paragraph in itself being of a substantial nature. All paragraphs are to be examined in the light of the requirements in Article 5. Member States may introduce provisions on the content of the environmental report that go further than the requirements of the Directive. A plan or programme can be very extensive and treat a great number of different issues so it should be emphasized that the Directive calls for information that concentrates on issues related to the significant effects on the environment of the plan or programme (see Article 5). An excessive account of information on insignificant effects or irrelevant issues makes the report difficult to digest and might lead to important information being overlooked.

(a) an outline of the contents, main objectives of the plan or programme and relationship with other relevant plans and programmes.

5.20. Information on the relationship with other relevant plans or programmes sets the plan or programme in a broader context: it might, for instance, concern its place in the stage of decision-making or its contribution amongst other plans or programmes to changes in the environmental conditions of a certain area. Relevant plans or programmes can thus be those at other levels in a hierarchy which the actual plan or programme forms part of or they can be those drawn up for other sectors affecting the same or adjacent areas.

(b) the relevant aspects of the current state of the environment and the likely evolution thereof without implementation of the plan or programme;

(c) the environmental characteristics of areas likely to be significantly affected;

(d) any existing environmental problems which are relevant to the plan or programme including, in particular, those relating to any areas of a particular environmental importance, such as areas designated pursuant to Directives 79/409/EEC and 92/43/EEC.

5.21. The requirements in (b), (c), and (d) may overlap but are coherent and they aim at different aspects of the environmental conditions in areas covered by the plan or programme and on which it is likely to have significant environmental effects. In (b) the concern is the state of the environment in all the area that is covered by or significantly affected by the plan or programme, currently as well as without its implementation. In (c) information is to be provided on the areas that are likely to be significantly affected by the plan or programme, information that can be seen as a specification of the information given under (b). The concern in (d) is focused on environmental problems while the aspects or characteristics in (b) and (c) could be problems as well as environmental values and assets or a favourable state of the environment. Since the requirements in (c) and (d) overlap, it might in many cases be appropriate to address them together, provided that all the necessary information is provided.

5.22. The information required in (b) on the relevant aspects of the current state of the environment is necessary for the understanding of how the plan or programme could significantly affect the environment in the area in question. The term 'the relevant aspects' refers to environmental aspects that are relevant to the likely significant environmental effects of the plan or programme. These aspects could be of a positive as well as of a negative nature. The information must concern the current state of the environment which means that it should be as up to date as possible. The description of the likely evolution of the relevant aspects without the implementation of the plan or programme is important as a frame of reference for the assessment of the plan or programme. This requirement can be seen as corresponding to the so-called zero-alternative often applied in environmental impact assessment procedures. The description of the evolution should cover roughly the same time horizon as that envisaged for the implementation of the plan or programme. Effects of other adopted plans or programmes, or decisions made that would affect the area in question, should also be considered in this respect so far as practicable.

5.23. In (c) the focus is on the areas that are of special interest for the assessment, namely the areas likely to be significantly affected by the plan or programme. A description of the environmental characteristics of these areas is to be given in the report. It would be appropriate to describe environmental characteristics by reference to the environmental issues listed in paragraph (f). Examples of characteristics could be that an area is specially sensitive or vulnerable to acidification, that it has high botanical value or that it is densely populated and many people will be affected by traffic noise. It should be noted that such areas could be found outside the area covered by the plan or programme. If this area is near to another Member State or if the effects are of a long-range nature, areas in other Member States and beyond could of course be significantly affected. In such cases transboundary consultation will be needed (see paragraphs 7.24 - 7.29).

5.24. Paragraph (d) asks for information on any existing environmental problems relevant to the plan or programme. The purpose of this information is to provide for an assessment of how these problems will affect the plan or programme or whether it is likely to aggravate, reduce or in any other way affect existing environmental problems. The relevance may also lie in the likely significant effects of the plan or programme, and also in non-significant effects that in combination with existing environmental problems could create significant effects. Even issues treated in the plan or programme which do not have any environmental effects may be relevant. The problems do not need to be of a significant nature and they do not need to be specially related to specific areas such as those exemplified in the text. Areas of particular environmental importance could be those with especially high environmental values, such as the areas designated under the Birds and Habitats Directives, but areas designated under national legislation could also be included.

(e) the environmental protection objectives, established at international, Community or Member State level, which are relevant to the plan or programme and the way those objectives and any environmental considerations have been taken into account during its preparation.

5.25. The environmental protection objectives to be dealt with should cover at least the issued listed in paragraph (f). International and Community objectives are often incorporated in objectives on national, regional and local levels and these could often be sufficient for this purpose. It should be noted that the paragraph concerns objectives that are relevant to the plan or programme, which would imply relevant to its likely significant effects or to issues it raises. Consultation with authorities according to Article 5(4) can help to provide this information. The German EIA Association has developed a prototype of a database on environmental quality objectives on international or community level. This can be found at: http://www.umweltdatenkatalog.de:8888/envdb/maintopic.jsp [now available on the German EIA-web - select 'Projects' on left then 'Database Environmental Protection Objectives on International or Community Level']

(f) the likely significant effects on the environment, including on issues such as biodiversity, population, human health, fauna, flora, soil, water, air, climatic factors, material assets, cultural heritage including architectural and archaeological heritage, landscape and the interrelationship between the above factors.

These effects should include secondary, cumulative, synergistic, short, medium and long-term permanent and temporary, positive and negative effects.

5.26. The list of issues in (f) is not exhaustive and other issues may be relevant. Compared to the list of the amended EIA Directive, human health, biodiversity and cultural heritage are here mentioned explicitly. The notion of human health should be considered in the context of the other issues mentioned in paragraph (f) and thus environmentally related health issues such as exposure to traffic noise or air pollutants are obvious aspects to study. Guidelines for incorporating biodiversity related issues in strategic environmental assessments have been adopted under the Convention on Biological Diversity. A description of the relationship between the factors mentioned in paragraph (f) is essential since it could show other and more severe significant effects than those resulting from a more isolated study of each single factor. Thus significant effects on air and climatic factors may cause significant adverse effects on flora, fauna and biodiversity. The purpose of the footnote is to emphasize the need for broad and comprehensive information on the factors and their interrelationship (although it should be read in the light of Article 5(2)). A description of positive effects is essential in order to show the contribution of the plan and programme to environmental protection and sustainable development.

(g) the measures envisaged to prevent, reduce and as fully as possible offset any significant adverse effects on the environment of implementing the plan or programme.

5.27. The purpose of paragraph (g) is to ensure that the environmental report discusses how the significant adverse effects it describes are to be mitigated. The measures envisaged in paragraph (g) are not specified further and they could be measures envisaged or prescribed in the plan or programme or measures discussed in the environmental report. It should be remembered that mitigation measures may themselves have adverse environmental effects which should be recognised. There exist methods of mitigation in connection with environmental impact assessments that could also be helpful for assessments of plans and programmes.

(h) an outline of the reasons for selecting the alternatives dealt with, and a description of how the assessment was undertaken including any difficulties (such as technical deficiencies or lack of know-how) encountered in compiling the required information.

5.28. Information on the selection of alternatives is essential to understand why certain alternatives were assessed and their relation to the draft plan or programme. A description of the methods used in the assessment is helpful when judging the quality of information, the findings and the degree to which they can be relied upon. An account of the difficulties met will also clarify this aspect. When appropriate, it would be helpful to include how those difficulties were overcome.

(i) a description of the measures envisaged concerning monitoring in accordance with Article 10.

5.29. According to Article 10 the significant environmental effects of the implementation of the plan or programme shall be monitored and, since these effects are specified in paragraph (f), the report should contain a description of how that monitoring is to be undertaken. The description should refer to existing monitoring arrangements if these are to be used. There is some overlap between paragraph (i) and the requirement in Article 9(1)(c) to make available at the time of adoption information on the 'measures decided concerning monitoring'. It is obvious that no definitive statement about the final monitoring measures can be made when the environmental report is still being prepared, since the content of the plan or programme is not decided, and in any event the content of the environmental report is subject to the criteria laid down in Article 5(2). Likewise, in some circumstances the monitoring arrangements may need to be adapted as implementation of the plan or programme proceeds. There appears to be nothing in the Directive to preclude this in appropriate cases.

(j) a non-technical summary of the information provided under the above headings.

5.30. The purpose of a non-technical summary, as required under paragraph (j), is to make the key issues and findings of the environmental report accessible and easily understood by the general public as well as by the decision-makers. The summary may be part of the report but it might also be helpful to make it available as a separate document to ensure a wider dissemination. An overall summary table may be helpful in simplifying the findings.

Notes

[14] Compare Article 5(3) and Annex IV of the EIA Directive which require the developer to provide an outline of the main alternatives studied and an indication of the main reasons for his choice taking into account the environmental effects.


4. GENERAL OBLIGATIONS

Top

6. QUALITY OF THE ENVIRONMENTAL REPORT