SEARCH   SITE MAP
UNUnited Nations Economic Commission for Europe

Convention on Environmental Impact Assessment (EIA) in a Transboundary Context

Resource Manual to Support Application of the Protocol on SEA

Draft Final

 

Implementation of Directive 2001/42 on the Assessment of the Effects of Certain Plans and Programmes on the Environment (the 'EC Guide')


2. OBJECTIVES OF THE DIRECTIVE

Table of Contents

4. GENERAL OBLIGATIONS

3. SCOPE OF THE DIRECTIVE [6]

3.1. The provisions determining the scope of application of the Directive are mainly expressed in two related articles. Article 2 sets out certain characteristics which plans and programmes must possess for the Directive to apply to them. Article 3 then sets out rules for determining which of those plans and programmes are likely to have significant effects on the environment and must therefore be subject to environmental assessment. Article 13(3) defines the temporal scope of application (see paragraphs 3.64-66 below).

Article 2

(a) 'plans and programmes' shall mean plans and programmes, including those co-financed by the European Community, as well as any modifications to them:

  • which are subject to preparation and/or adoption by an authority at national, regional or local level or which are prepared by an authority for adoption, through a legislative procedure by Parliament or Government, and
  • which are required by legislative, regulatory or administrative provisions.

3.2. The first requirement, in order for plans and programmes to be subject to the Directive, is that they must meet the conditions of both indents in Article 2(a). In other words, they must be both 'subject to preparation and/or adoption by the prescribed authorities' and 'required by legislative, regulatory or administrative provisions'.

3.3. Plans and programmes are not further defined. The words are not synonymous but they are both capable of a broad range of meanings which at some points overlap. So far as the Directive's requirements are concerned, they are treated in an identical way. It is therefore neither necessary nor possible to provide a rigorous distinction between the two. In identifying whether a document is a plan or programme for the purposes of the Directive, it is necessary to decide whether it has the main characteristics of such a plan or programme. The name alone ('plan', 'programme', 'strategy', 'guidelines', etc) will not be a sufficiently reliable guide: documents having all the characteristics of a plan or programme as defined in the Directive may be found under a variety of names.

3.4. In considering the concept of 'project' under the EIA Directive in case C-72/95 Kraaijeveld, the ECJ noted that that Directive had a wide scope and a broad purpose. In view of the language used in Directive 2001/42/EC, the related purposes of that Directive and the EIA Directive, and the conceptual similarities between them, Member States are advised to adopt a similar approach in considering whether an act is to be considered a plan or a programme falling within the scope of Directive 2001/42/EC. The extent to which an act is likely to have significant environmental effects may be used as one yardstick. It may be that the terms should be taken to cover any formal statement which goes beyond aspiration and sets out an intended course of future action.

3.5. The kind of document which in some Member States is thought of as a plan is one which sets out how it is proposed to carry out or implement a scheme or a policy. This could include, for example, land use plans setting out how land is to be developed, or laying down rules or guidance as to the kind of development which might be appropriate or permissible in particular areas, or giving criteria which should be taken into account in designing new development. Waste management plans, water resources plans, etc, would also count as plans for the purposes of the Directive if they fall within the definition in Article 2(a) and meet the criteria in Article 3. [7]

3.6. In some Member States, programme is usually thought of as the plan covering a set of projects in a given area, for example a scheme for regeneration of an urban area, comprising a number of separate construction projects, might be classed as a programme. In this sense, 'programme' would be quite detailed and concrete. One good example of such a programme could be the Icelandic Integrated Transportation Programme which is planned to take the place of independent programmes for road, airport, harbour and coastal defence projects. The transport infrastructure is defined and policy on transport infrastructure is laid out for a period of 12 years (identifying projects by name, location and cost). But these distinctions are not clear cut and need to be considered case by case. Other Member States use the word 'programme' to mean 'the way it is proposed to carry out a policy' - the sense in which 'plan' was used in the previous paragraph. In town and country planning in Sweden, for instance, the programme is thought of as preceding a plan and as being an inquiry into the need for, and appropriateness and feasibility of, a plan.

3.7. Plans and programmes include those co-financed by the European Community. The Directive is of course addressed only to the Member States and not to the institutions of the Community. [8] Regardless of the decision-making process within the Community institutions regarding funding (and whether or not there is SEA - or an analogous form of assessment - by those institutions) there will need to be an assessment by the Member State if the plan or programme is subject to the Directive.

3.8. If the criteria in Articles 2 and 3 are met, the Directive would apply in principle to co-financed plans in several sectors, including transport and regional, economic and social development (Structural Funds). [9] Article 11(3) prescribes expressly that for plans and programmes co-financed by the European Community, the environmental assessment under Directive 2001/42/EC must be carried out in conformity with the specific provisions of the relevant Community legislation. Hence the assessment must comply with each requirement of the applicable legislation; an assessment adequate for one Directive may not be adequate for any other which applies. Plans and programmes co-financed under the current respective programming periods of Regulations 1260/1999/EC and 1257/1999/EC are exempted from the scope of the SEA Directive. This is because plans and programmes under those Regulations will almost certainly have been agreed before the Directive is due to be transposed in the Member States (i.e. 21st July 2004) and will have undergone prior environmental assessment. The exemption does not apply to future programming periods under those Regulations and Article 12(4) requires the Commission to report on the relationship between the Directive and the Regulations before the expiry of the current programming periods.

3.9. The definition of plans and programmes includes modifications to them. Many plans, especially land use plans, are modified when they eventually become outdated rather than being prepared afresh. Such modifications are treated in the same way as plans and programmes themselves and require environmental assessment provided the criteria laid down in the Directive are met. If such modifications were not given the same importance as the plans and programmes themselves, the field of application of the Directive would be more restricted. [10] The adoption of such modifications will be subject to an appropriate procedure. It is important to distinguish between modifications to plans and programmes, and modifications to individual projects, envisaged under the plan or programme. In the second case, (where individual projects are modified after the adoption of the plan or programme), it is not Directive 2001/42/EC but other appropriate legislation which would apply. An example could be a plan for road and rail development, including a long list of projects, adopted after SEA. If, in implementing the plan or programme, a modification were proposed to one of its constituent projects and the modification was likely to have significant environmental effects, an environmental assessment should be made in accordance with the appropriate legal provisions (for example, the Habitats Directive, and/or EIA Directive).

3.10. Under Article 5 of Directive 2001/42/EC, the likely significant effects on the environment of implementing the plan or programme must be identified, described and evaluated. Thus it is logical to consider that a modification of a plan or a programme during its preparation must be subject to assessment under Article 5 if the modification in itself involves significant environmental effects not yet assessed. This might arise if a modification was made as a result of consultation, or of reconsideration of elements of the plan or programme, or if the state of the environment had changed so as to make assessment necessary. Even minor modifications can generate significant environmental effects, as foreseen in Article 3(3) of the Directive. Delays might ensue in the adoption of the plan or programme but these should be kept to a minimum, subject to the over-riding requirement to assess the likely significant environmental effects.

3.11. The element subject to preparation and/or adoption by an authority stresses that plans and programmes need to fulfil certain formal conditions in order to be covered by the Directive. The main idea of this element is that in the end a plan or programme would always be formally adopted by an authority. However, the phrase would also include the situation where a plan is prepared by one authority (or natural or legal person who works on behalf of the authority) and is adopted by another authority.

3.12. The concept of an 'authority' has been given a large scope in the case law of the ECJ. It can be defined as a body, whatever its legal form and regardless of the extent (national, regional or local) of its powers, which has been made responsible, pursuant to a measure adopted by the State, for providing a public service under the control of the State, and it has for that purpose special powers beyond those which result from the normal rules applicable in relations between individuals (case C-188/89 Foster and others v British Gas). For example, privatised utility companies may be required to carry out some tasks or duties (such as preparing long-term plans for ensuring water resources) which in non-privatised regimes would be carried out by public authorities. In respect of those functions they would be treated as authorities for the purposes of the Directive. In other respects (such as providing consultancy services overseas) they would not be considered to be authorities in the sense of the Directive.

3.13. Plans and programmes which private bodies draw up for their own purposes (i.e. when not acting as authorities as described above, nor as agents of authorities, and when not preparing them for adoption by authorities) are not subject to the Directive.

3.14. Preparation of a plan or programme covers a process which lasts right through to its adoption. Adoption through a legislative procedure by Parliament or Government is one procedure for adopting plans and programmes in some Member States. For example, in Italy regional and local Territorial and Urban plans are adopted and approved in a two-stage procedure by the relevant regional or local authorities. The final approval is often by means of a regional law. 'Government' is not restricted to the level of the State. In some countries, plans and programmes may be adopted by primary or secondary legislation of any State, regional or local legislature. These cases, too, are subject to environmental assessment when the other requirements of the Directive are met. One example at national level is the French Schémas de services collectives which are prepared at national level, with consultation at regional level, and approval by the Government after consultation with Parliament.

3.15. Another important qualification for a plan or programme to be subject to the Directive is that it must be required by legislative, regulatory or administrative provisions. If these conditions are not met, the Directive does not apply. Such voluntary plans and programmes usually arise because legislation is expressed in permissive terms, [11] or because an authority decides to prepare a plan on an activity which is unregulated. On the other hand, if an authority is not required to draw up a plan unless certain preconditions are met, it would probably be subject to the Directive once those preconditions had been met (and the other requirements of Articles 2 and 3 had been fulfilled). It is of course open to Member States, in respect of their own national systems, to go further than the minimum requirements of the Directive should they so desire.

3.16. Administrative provisions are formal requirements for ensuring that action is taken which are not normally made using the same procedures as would be needed for new laws and which do not necessarily have the full force of law. Some provisions of 'soft law' might count under this heading. Extent of formalities in its preparation and capacity to be enforced may be used as indications to determine whether a particular provision is an 'administrative provision' in the sense of the Directive. Administrative provisions are by definition not necessarily binding, but for the Directive to apply, plans and programmes prepared or adopted under them must be required by them, as is the case with legislative or regulatory provisions.

Article 3

3.17. Article 3 sets out the scope of application of the Directive and is fundamental to its operation. It begins by expressing the requirement for an environmental assessment of certain plans and programmes which are likely to have significant environmental effects (paragraph 1). It then defines classes of plans and programmes which require assessment, either automatically (paragraph 2) or on the basis of a determination by Member States (paragraphs 3 and 4). Paragraph 5 specifies how that determination (so-called 'screening') should be made.

3.18. Paragraphs 6 and 7 deal with transparency aspects of the determination under paragraph 5, and paragraphs 8 and 9 list certain plans and programmes exempted from the scope of the Directive.

3.19. The point in time from which these provisions apply is defined in Article 13(3) of the Directive.

Article 3(1)

An environmental assessment, in accordance with Articles 4 to 9, shall be carried out for plans and programmes referred to in paragraphs 2 to 4 which are likely to have significant environmental effects.

3.20. Article 3(1) is the starting point for the more detailed provisions which follow in the remainder of the Article. The assessment to be carried out must be in accordance with Articles 4 to 9, and the plans and programmes to be assessed are specified in paragraphs 2 to 4.

3.21. The relationship between paragraph 1 and paragraphs 2 to 4 is clarified by Recital 10. It is important to note that the plans and programmes defined in paragraph 2 should as a rule be made subject to systematic environmental assessment. Except in the cases provided for in paragraph 3, there is no discretion for Member States to determine whether the plans and programmes covered by paragraph 2 are in fact likely to have significant environmental effects: the Directive deems them to have such effects. By contrast, Member States must determine whether plans and programmes not referred to in paragraph 2, which set the framework for future development consent of projects, are likely to have significant environmental effects and therefore, in accordance with paragraph 1, require environmental assessment.

Article 3(2)

Subject to paragraph 3, an environmental assessment shall be carried out for all plans and programmes,

(a) which are prepared for agriculture, forestry, fisheries, energy, industry, transport, waste management, water management, telecommunications, tourism, town and country planning or land use and which set the framework for future development consent of projects listed in Annexes I and II to Directive 85/337/EEC, or

(b) which, in view of the likely effect on sites, have been determined to require an assessment pursuant to Article 6 or 7 of Directive 92/43/EEC.

3.22. Paragraph 2 defines two classes of plans and programmes which are deemed likely to have significant environmental effects. For a plan or programme to fall within the scope of paragraph 2(a), both conditions described there must have been fulfilled; the plan or programme must have been prepared for one or more of the sectors (agriculture, forestry, fisheries, etc) and it must set the framework for future development consent of projects listed in the EIA Directive. It is not necessary to decide whether projects in Annex II to that Directive would require EIA. All that is necessary is that they fall under the categories listed in either Annex I or II to the EIA Directive.

3.23. The meaning of 'set the framework for future development consent' is crucial to the interpretation of the Directive, although there is no definition in the text. The words would normally mean that the plan or programme contains criteria or conditions which guide the way the consenting authority decides an application for development consent. Such criteria could place limits on the type of activity or development which is to be permitted in a given area; or they could contain conditions which must be met by the applicant if permission is to be granted; or they could be designed to preserve certain characteristics of the area concerned (such as the mixture of land uses which promotes the economic vitality of the area).

3.24. The words 'sets a framework for projects and other activities' are used in Annex II with illustrations of how such a framework may be set (location, nature, size or operating conditions of projects and the allocation of resources). These illustrations are indicative and not exhaustive.

3.25. As Annex II states, one way of 'setting the framework' may be through the way resources are allocated but the exemptions in Article 3(8) should be borne in mind. The Directive does not define the meaning of 'resources' and in principle they may be financial or natural (or possibly even human). A generalised allocation of financial resources would not appear to be sufficient to 'set the framework', for example a broad allocation across an entire activity (such as the whole resource allocation for a country's housing programme). It would be necessary for the resource allocation to condition in a specific, identifiable way how consent was to be granted (e.g. by setting out a future course of action (as above) or by limiting the types of solution which might be available).

3.26. Land use plans generally contain criteria determining what kind of development can take place in particular areas and are a typical example of plans which set the framework for future development consent. An example of the latter is the Netherlands' Municipal Land Use Plans which in some cases set conditions for the granting of building permits by municipalities. Whether particular criteria or conditions set the framework in individual cases will be a matter of fact and degree in each case: a single constraining factor may be so significant that it has a dominant influence on future consents. On the other hand, several rather trivial or imprecise factors may have no influence on the granting of consents.

3.27. The phrase could include plans and programmes which, when adopted, themselves give consent for projects, provided these comply with the conditions set out in the plan or programme. Such provisions exist in several Member States. It could include the plans and programmes which, in some countries, set legally binding conditions with which future development consents must conform.

3.28. The phrase could also include sectoral plans and programmes which in broad terms identify the location of subsequent development within that sector. It would be necessary in each case to consider the extent to which future decisions on projects were conditioned by the plan or programme.

3.29. Article 3(2) expressly refers to 'projects' listed in the EIA Directive. There 'project' is defined as:

  • the execution of construction works or of other installations or schemes,
  • other interventions in the natural surroundings and landscape including those involving the extraction of mineral resources.

3.30. The word 'project' should be interpreted in a way which is consistent with its use in the EIA Directive. The same should hold good for the use of the word in Article 3(4), given the conceptual and linguistic similarities between the two provisions.

3.31. Town and country planning plans and land use plans deal with the way land is to be developed or redeveloped. The terms may be used in different ways by different Member States, but generally both deal with the way territory is to be used, even if one may comprise a broader concept than the other.

3.32. Article 3(2)(b) refers to Articles 6 and 7 of Directive 92/43/EEC (the Habitats Directive). Those Articles require an 'appropriate assessment' of 'any plan or project not directly connected with or necessary to the management of a site but likely to have a significant effect thereon'. Hence, if a plan [12] has been found to have significant environmental effects under Article 6(3) of Directive 92/43 on a certain site or sites, this finding triggers the application of the SEA Directive under this paragraph. The sites at issue are those designated as special protection areas (SPA) under Article 4 of Directive 79/409 on the conservation of wild birds and those proposed to be classified as sites of Community importance (pSCI) under Article 4 of Directive 92/43 on the conservation of natural habitats and of wild fauna and flora.[13] In accordance with Article 11(2), integrated assessments are possible meeting the requirements of several items of Community legislation at the same time, in order to avoid duplication of assessment procedures. On the question of avoiding duplication of assessment see paragraphs 9.13 and 9.19-9.27 below.

Article 3(3)

Plans and programmes referred to in paragraph 2 which determine the use of small areas at local level and minor modifications to plans and programmes referred to in paragraph 2 shall require an environmental assessment only where the Member States determine that they are likely to have significant environmental effects.

3.33. The meaning of 'small' in the phrase 'small areas at local level' must be defined so as to take account of the differences between Member States and it will probably be necessary to decide it case by case. Interpretation will call for the careful exercise of judgement. The kind of plan or programme envisaged might be a building plan which, for a particular, limited area, outlines details of how buildings must be constructed, determining, for example, their height, width or design.

3.34. There is a similar difficulty in deciding the meaning of 'local'. The language of the Directive does not establish a clear link with local authorities but the word 'level' does imply a contrast with, for example, national or regional levels. The complete phrase ('small areas at local level') makes it clear that the whole of a local authority area could not be excluded (unless it were itself small). In some Member States local authority areas can be very large indeed and an exemption for the whole of such an area would be a major loophole in the scope of application.

3.35. The key criterion for the application of the Directive, however, is not the size of area covered but whether the plan or programme would be likely to have significant environmental effects. A plan or programme which Member States determine likely to have significant environmental effects should undergo environmental assessment even if it determines only the use of a small area at local level. A similar point was made in Case C-392/96, Commission v Ireland, where the ECJ ruled that by setting thresholds on the basis of the size of projects alone, 'to the exclusion of their nature and location', the Member State exceeded the limits of its discretion. Projects could have significant effects on the environment by reason of their nature or location.

3.36. Similarly, minor modifications should be considered in the context of the plan or programme which is being modified and of the likelihood of their having significant environmental effects. A general definition of 'minor modifications' would be unlikely to serve any useful purpose. Under the definition of 'plans and programmes' in Article 2 'any modifications' to those plans or programmes are potentially within the scope of the Directive. Article 3(3) clarifies the position by recognising that a modification may be of such small order that it is unlikely to have significant environmental effects, but requiring that where the modification of a plan or programme is likely to have significant environmental effects then an assessment should be carried out regardless of the scale of the modification. It is important to note that not all modifications would require new impact assessment under the Directive since it does not require such new procedures to be triggered if the modifications are not likely to have significant environmental effects.

Article 3(4)

Member States shall determine whether plans and programmes, other than those referred to in paragraph 2, which set the framework for future development consent of projects, are likely to have significant environmental effects.

3.37. Article 3(4) broadens the scope of the Directive. Unlike Article 3(2), it does not automatically deem certain plans and programmes to have significant environmental effects. Instead it requires Member States to make a specific determination. The plans and programmes to which it applies are all those which set the framework for future development consent of projects but are not covered by Article 3(2). This includes projects in sectors not included in Article 3(2) as well as projects which are in those sectors but are not listed in the annexes to the EIA Directive. The definition of 'project' in the EIA Directive would apply in this paragraph as it does in paragraph 2. The meaning of set the framework for future development consent of projects was discussed under Article 3(2) above.

Article 3(5)

Member States shall determine whether plans or programmes referred to in paragraphs 3 and 4 are likely to have significant environmental effects either through case-by-case examination or by specifying types of plans and programmes or by combining both approaches. For this purpose Member States shall in all cases take into account relevant criteria set out in Annex II, in order to ensure that plans and programmes with likely significant effects on the environment are covered by this Directive.

3.38. As described above, Article 3(3) and (4) sets out the circumstances in which Member States have to determine whether a plan or programme is likely to have significant environmental effects. Article 3(5) prescribes how they are to discharge this general requirement, while Annex II identifies criteria to guide the determination (the so-called 'significance criteria').

3.39. Plans and programmes referred to in paragraphs 3 and 4 are of two kinds: (i) special cases of plans and programmes falling under paragraph 2; and (ii) plans and programmes other than those in paragraph 2 which set the framework for the future development consent of projects.

3.40. Following the model provided by the EIA Directive, Directive 2001/42/EC provides for three approaches (or 'screening mechanisms') to making this determination: case-by-case examination, specifying types of plans and programmes, or combining both approaches.

3.41. A case-by-case examination would require each plan or programme to be examined on an individual basis to see whether it is likely to have significant effects on the environment. This approach has the advantage of being best able to take individual situations and the characteristics of each plan or programme into account but at the cost of some added administrative burden.

3.42. By 'specifying types of plans and programmes' the Directive envisages that plans and programmes of the same kind will be the subject of a general determination that they are likely to have significant environmental effects. This approach has the advantage of legal and administrative certainty since it is made clear from the start that an environmental assessment is necessary.

3.43. It is clear that the power in Article 3(5) to specify types of plans and programmes is not intended as a broad power to exempt whole classes of plans and programmes unless all those plans and programmes could, when viewed as a whole, be regarded as not being likely to have significant effects on the environment (see Case C-72/95 Kraaijeveld). Insofar as it could represent a derogation from the Directive, it should be interpreted narrowly (see the comment at paragraph 65 of Case C-435/97 Autonome Provinz Bozen). In practice, exclusion from environmental assessment may not be justified in many cases. It might well be that at the outset not enough information is available at the plan or programme level to be sure that none of the plans or programmes in the proposed class will have significant environmental effects. Furthermore, care would be needed to avoid pre-empting decisions on the application of the Directive to future plans and programmes which might not share all the characteristics of the class in question. For example, changes in the law might create new plans and programmes which would need consideration in order to determine whether the Directive applied to them.

3.44. A combination of both approaches (case by case examination and specifying types of plans or programmes) might be possible in some cases. The general approach would be to define a class of plans or programmes which would not, in specified circumstances, be likely to have significant environmental effects and to provide that in other circumstances the determination would have to be made case by case.

3.45. Article 3(5) of the Directive specifically requires Member States to take account of relevant criteria in Annex II when determining whether plans or programmes are likely to have significant effects on the environment. The wording of the Directive implies that the whole set of Annex II criteria first needs to be considered so that the relevant ones can then be applied. Expert judgement can help to apply relevant criteria to the plan or programme in order to reach a decision about the likely significance of its effects.

3.46. Different issues have to be taken into account when screening mechanisms are developed. The criteria in Annex II are divided into two categories: the characteristics of plans or programmes, and the environmental effects and the area likely to be affected. Cases of doubt about whether environmental assessment is needed are often likely to reflect uncertainty about the effects of the plan or programme. Further consideration by appropriate experts may resolve the doubt, if not it is recommended that environmental assessment should be carried out. Although Article 3(5) does not explicitly refer to Annex I, it may also be useful to consider the environmental factors identified there.

3.47. Careful consideration is needed of how the criteria in Annex II ('significance criteria') should be applied when specifying types of plans and programmes. In principle, the determination could be made by prescribing qualitative criteria or thresholds based on the relevant significance criteria. It is advisable to avoid screening systems which are based only on the size or financial thresholds of projects, or on the physical area covered by the plan or programme, as these may not comply with the Directive.

Annex II: Criteria for determining the likely significant effects

3.48. The list in Annex II contains criteria relating to the characteristics of the plan or programme (paragraph 1), and the effects and area likely to be affected (paragraph 2). They are not listed in order of importance. Their individual importance will be different as between cases. In general, it can be assumed that the greater the degree to which the criteria are met the more likely it is that the effects on the environment will be significant. It may be, however, that in some cases the effects related to a single criterion are so important as to trigger the need for SEA. In such cases, the screening procedure can be abbreviated accordingly but usually a more comprehensive consideration will be needed.

3.49. The criteria listed in Annex II are not exhaustive and the Directive does not prevent Member States from requiring additional criteria to be taken into consideration.

3.50. Throughout the text of the Directive environmental assessment is connected with the likelihood of significant environmental effects. The prediction of likely environmental effects is complex, especially in the context of relatively broad-brush, or high level plans or programmes, where it may be difficult to anticipate the outcomes of implementation at the time a plan or programme is adopted. The use of the word 'likely' suggests that the environmental effects to be considered are those which can be expected with a reasonable degree of probability.

The degree to which the plan or programme sets a framework for projects and other activities, either with regard to the location, nature, size and operating conditions or by allocating resources

3.51. The more precisely the framework is set by a plan or programme, the more likely it is that an assessment under the Directive will be required. Hence plans or programmes which define, for example, not only the area for building houses or commercial activities but also their nature, size and (as appropriate) operating conditions, might establish a more detailed framework for projects than plans or programmes which define objectives without specifying details of the framework within which they must be achieved. Plans or programmes which are legally binding might set the framework more strictly than nonbinding plans or programmes. Plans or programmes whose only or main purpose is to set a framework for projects might also set a stronger framework than plans or programmes which have several different purposes and issues.

The degree to which the plan or programme influences other plans and programmes including those in a hierarchy

3.52. If a plan or programme strongly influences another, any environmental effects it might have may be spread more widely (or deeply) than if this were not the case. Schematically, plans and programmes can be divided into two categories, 'horizontal' (plans and programmes belonging to the same level, or having an equal or similar status) and 'vertical' (plans and programmes belonging to a hierarchy). In a hierarchy, plans and programmes at the higher, general level might influence those at a lower, detailed level. For example, those at the lower level might have to take account explicitly of the contents or objectives of the plan or programme at the higher level or might have to demonstrate how they contribute to the objectives expressed in the higher level plan. It is of course clear that in practice things may be less straightforward; in particular, in some systems the lower level plan or programme might sometimes (e.g. if it were more recent) influence the one at a higher level. Binding plans or programmes, which will be explicitly implemented by means of other plans or programmes will probably have a strong influence. The legal aspect of a plan or programme - is it binding or not - may play a determining role in some systems. Plans or programmes which are the only ones in a sector and do not belong to a hierarchy might have less possibility of influencing other plans or programmes. This is not a foregone conclusion and the relationships between different plans and programmes will have to be carefully considered in each case.

The relevance of the plan or programme for the integration of environmental considerations in particular with a view to promoting sustainable development

3.53. The question to be addressed in this context is how far the plan or programme envisaged can contribute to reducing harm to the environment. A plan or programme which has great scope to affect the environment will be a strong candidate for assessment whilst one with few environmental implications may not be. For example, integrating the environment in, say, an education plan is a desired outcome. There is unlikely to be much scope for this in a plan about the contents of school curricula (even assuming that it sets the framework for projects); but plans about school accommodation may well be candidates for environmental assessment as they have a considerable potential to influence travel and possibly housing patterns.

3.54. In addition, an assessment may help to find ways of improving the environmental outcome of a plan or programme, or its contribution to sustainable development, at no greater cost; in reducing the cost of environmental safeguards whilst enabling other objectives to be met; or in choosing between alternatives.

environmental problems relevant to the plan or programme

3.55. The relevance of the problems to the plans or programmes is not defined and could be interpreted in several ways. It would include cases where plans or programmes either cause or exacerbate environmental problems, are constrained or otherwise affected by them, or contribute to solving, reducing or avoiding them. In any case it will be necessary to identify the nature and seriousness of environmental problems relevant to the plan or programme.

the relevance of the plan or programme for the implementation of Community legislation on the environment (e.g. plans and programmes linked to waste-management or water protection)

3.56. The Directive uses a rather neutral word ('relevance') in this criterion. Both positive and negative contributions to the implementation of Community legislation need to be considered here. It is important to ensure that the full range of Community legislation on the environment is taken into account

the probability, duration, frequency and reversibility of the effects,

the cumulative nature of the effects,

the transboundary nature of the effects,

the risks to human health or the environment (e.g. due to accidents),

the magnitude and spatial extent of the effects (geographical area and size of

the population likely to be affected),

the value and vulnerability of the area likely to be affected due to:

  • special natural characteristics or cultural heritage,
  • exceeded environmental quality standards or limit values,
  • intensive land-use,

the effects on areas or landscapes which have a recognised national, Community or international protection status.

3.57. Many uncertainties exist, and insufficient or missing data and inadequate knowledge may make it difficult to decide whether significant effects are likely. Nevertheless, it is assumed that a rough estimation of the effects should always be possible.

3.58. The nature and characteristics of the likely effects will influence their significance in the context within which they are being considered. For example, it is relevant to consider whether the probability or frequency of effects will be very low (accidental cause) or whether the effects will occur continuously. Moreover, the more complex (e.g. due to synergies and accumulation), the more widespread, or the more serious the effects, the more likely it is that they should be considered 'significant'.

3.59. An equally important factor to be considered is the area likely to be affected by the plan or programme and consequently by its effects. It should be noted that it is not only areas that have a designated protection status which are required by the Directive to be given attention. The particular value or vulnerability of the area likely to be affected may make it more likely that effects must be considered significant there.

3.60. This was a point considered by the ECJ in case C-392/96 Commission v Ireland (referred to above). There the Court said: 'Even a small-scale project can have significant effects on the environment if it is in a location where the environmental factors set out in Article 3 of the [EIA] Directive, such as fauna and flora, soil, water, climate or cultural heritage, are sensitive to the slightest alteration. Similarly, a project is likely to have significant effects where by reason of its nature, there is a risk that it will cause a substantial or irreversible change in those environmental factors, irrespective of its size.'

3.61. Applying the criteria for determining potential environmental effects requires a comprehensive and systematic approach. To enable this to be achieved, some of the elements identified in Annex I may also be relevant. For example, for identifying likely significant effects the 'receptors' of these effects should be considered (see the list of issues in Annex I (f), i.e. biodiversity, population, human health, fauna, flora, soil, water, air, climatic factors, material assets, cultural heritage including architectural and archaeological heritage, landscape and the interrelationship between these factors). The characteristics noted in the footnote to Annex I(f) should also be taken into account (i.e. whether the effects are secondary, cumulative, synergistic, short, medium and long-term permanent and temporary, positive and negative). The use of Annex I together with Annex II in this way enables cross-media effects to be considered in a multidisciplinary way.

Article 3(8)

The following plans and programmes are not subject to this Directive:

  • plans and programmes the sole purpose of which is to serve national defence or civil emergency,
  • financial or budget plans and programmes.

3.62. The exemption of plans and programmes 'the sole purpose of which' is to serve national defence or civil emergency is a stricter test than in the EIA Directive (which does not apply to 'projects serving national defence purposes'). This means that, for example, a regional land use plan which made provision for a national defence project in some part of the area it covered would require environmental assessment (provided the other criteria in the Directive were met) because to serve national defence was not its sole purpose. In applying this exemption, it is the purpose of the plan or programme which must be considered, not its effects. For example, an army base which is planned solely to serve national defence may have the additional effect of increasing local employment opportunities. It would still fall within this exemption. Civil emergency could include events having a natural or a man-made cause (e.g. earthquakes and terrorist activities respectively). There is no indication of when such plans and programmes should be drawn up; but their sole purpose must be to serve national defence or civil emergency. In line with the jurisprudence of the ECJ, the derogation should be construed narrowly. Thus a plan setting out what action should be taken if an avalanche were to occur would be exempt from the Directive, whereas one setting out measures to be taken to avoid avalanches occurring (perhaps through the provision of infrastructure) would not, because it would be intended to prevent an emergency rather than serve it.

3.63. Budgetary plans and programmes would include the annual budgets of authorities at national, regional or local level. Financial plans and programmes could include ones which describe how some project or activity should be financed, or how grants or subsidies should be distributed.

Article 13(3)

The obligation referred to in Article 4 (1) shall apply to the plans and programmes of which the first formal preparatory act is subsequent to the date referred to in paragraph 1 . Plans and programmes of which the first formal preparatory act is before that date and which are adopted or submitted to the legislative procedure more than 24 months thereafter, shall be made subject to the obligation referred to in Article 4(1) unless Member States decide on a case by case basis that this is not feasible and inform the public of their decision.

3.64. The obligation referred to in article 4(1) includes all the stages of an 'environmental assessment' as defined in Article 2 (i.e. environmental report, consultation, etc). It therefore implies the process of preparing a plan or a programme in the light of the emerging understanding of its environmental effects.

3.65. The word 'formal' does not necessarily mean that the act should be required by national law, nor whether it produces legal effects in national law. A judgement should be made in each case, taking into account factors such as the nature of the act in question, the nature of the steps preceding it, and the apparent aim of the transitional provision, namely to pursue legal certainty and good administration.

3.66. The second sentence of Article 13(3) is intended to ensure that an environmental assessment complying with the Directive will normally be carried out for plans and programmes of which the first formal preparatory act was before 21st July 2004 but which will not be adopted until after 21st July 2006. This implies that only minor or non- significant work would have been done on the plan by July 2004 in order to carry out a meaningful assessment. It would not be feasible to carry out an environmental assessment of a plan whose first preparatory act was before July 2004 and which was at a very advanced stage at that date. The focus of this provision is not so much on how long before July 2004 was the starting date of the plan or programme, but on whether the planning process of relevant plans or programmes is at a stage at which a meaningful environmental assessment can be carried out.

Notes

[6] In the jargon of environmental assessment, 'scope' usually refers to the coverage of the environmental report described in Article 5. This is not to be confused with the term 'scope' as used in the title of Article 3 to refer to the scope of application of the Directive.

[7] In Case C-387/97 (Commission v Greece), the ECJ considered what would not qualify as the plans which the Member States are required to adopt under Article 6 of Directive 75/442 and Article 12 of Directive 78/319. It said that 'legislation or specific measures amounting only to a series of ad hoc normative interventions that are incapable of constituting an organised and coordinated system for the disposal of waste and toxic and dangerous waste cannot be regarded as [such] plans' (paragraph 76).

[8] The Commission has introduced a procedure for assessing the impact of its own proposals (Communication on impact assessment, of 5 June 2002 (COM(2002)276 final)).

[9] 'Structural funds' are taken to include the European Regional Development Fund, the European Social Fund, the European Agricultural Guidance and Guarantee Fund, and the Financial Instrument for Fisheries Guidance (see Regulation 1260/1999/EC).

[10] See also Case C-72/95 (Kraaijeveld) which dealt with a similar point in relation to the EIA Directive before its amendment by Directive 97/11/EC.

[11] 'The authority may prepare a plan', rather than 'The authority shall prepare a plan'.

[12] It is to be noted that Article 6(3) covers plans and projects, not programmes.

[13] See the document 'Managing Natura 2000 sites: The provisions of Article 6 of the 'Habitats' Directive 92/43/EEC'.


2. OBJECTIVES OF THE DIRECTIVE

Top

4. GENERAL OBLIGATIONS