SEARCH   SITE MAP
UNUnited Nations Economic Commission for Europe

Protocol on Strategic Environmental Assessment (SEA)

Implementation of Directive 2001/42 on the Assessment of the Effects of Certain Plans and Programmes on the Environment (the 'EC Guide')


9. RELATION WITH OTHER EC LEGISLATION

Table of Contents

 

Appendix I Practical Guidance on Monitoring
Appendix II Members of the working group
Appendix III Bibliography

Appendix I - Practical guidance on monitoring

As guidance for the authorities in Member States which are responsible for integrating the monitoring requirements of Directive 2001/EC/42 into the different planning procedures, the following section describes several steps which could provide assistance.. These steps put the different issues into a logical order, but they do not represent a necessary chronological sequence. Moreover, knowledge and practical experience as regards monitoring of plans and programmes is at this stage relatively limited. Monitoring schemes should therefore be flexible and allow for adaptations as necessary.

More detailed information on the practical implementation of Article 10 can be obtained from the report 'Implementing Article 10 of the SEA Directive' prepared in the framework of the IMPEL Network.

Determination of the scope of monitoring

The first step to design a monitoring system for a given planning process is to define what environmental effects the monitoring system needs to cover. The environmental report sets a framework for the scope of monitoring by identifying the likely significant environmental effects. The environmental effects to be monitored are therefore in principle the same as those of the environmental assessment. However, depending on the type of plan or programme and in particular on the stage of its implementation it may be appropriate to focus on those environmental effects which are relevant with respect to the implementation. Further, the possibility of undertaking remedial actions may be considered when determining the scope of monitoring. Also scientific difficulties in establishing a clear link between the implementation of a plan or programme and changes in the environment may be an obstacle to monitor all environmental effects. Additionally a safety check should be performed in order to make sure that no adverse effect of the plan or programme has been overlooked in the assessment.

  • Monitoring covers in principle the environmental effects included in the environmental report.
  • It may, however, focus on some environmental effects or include additional aspects which were not apparent.

Identification of necessary information

The second step is the identification of the necessary information for finding out the environmental impacts of a plan or programme. Information about the environmental effects of a plan or programme can also be gained from the causes of the relevant effects,[23] since the effect of the plan or programme on the environment can be monitored directly (measuring changes in the environment) or indirectly through collecting information for example on the implementation of (mitigation) measures foreseen in the plan or programme or pressure factors such as emissions or the amount of waste.

Monitoring schemes which have been examined in the course of the IMPEL project on monitoring showed a tendency to focus rather on the implementation of measures and pressure factors than on the impact. The reason for this can be seen in the difficult establishing of the cause-effect link, i.e. to attribute a change in the environment which may be influenced by various factors unambiguously to the implementation of a plan or programme. A biological monitoring system, for example, may reveal comprehensive information about the status of the environment in a given area and about its change in a given period of time, but it may not contain any findings about whether a given change in the environment (e.g. loss of a certain species, damage to certain plants) can be attributed to the implementation of a certain traffic plan. Here the data from a biological monitoring system could be combined with an analysis of the progress of implementing the traffic plan ('driving forces') and the mitigation measures foreseen in the plan.

It should be noted that not all environmental information that might be available for the planning territory is automatically necessary and useful for the purpose of monitoring. The crucial point is to identify those data which are relevant and representative for the plan or programme. A feasible approach to select relevant environmental information was presented at the IMPEL project on monitoring. The monitoring arrangements for the waste management plan of Vienna were based on a set of questions which were relevant for the follow-up of the plan (e.g. prognosis about the amount of waste in the coming years; prognosis about emissions reductions; achievement of targets, etc.)[24] . Also a set of indicators will in many cases be used as a framework for the selection of relevant environmental information. A key function of indicators or a set of questions used in Vienna is to condense environmental data to information which is understandable also for non-experts (who usually will decide on further action).

Of course, reliability and the availability of the respective data within the planning period should also be taken into account when determining what environmental data are needed.

  • It is useful to identify and select the environmental information which is necessary for monitoring the relevant environmental effects.
  • Environmental effects may also be indirectly monitored through monitoring the causes of the effects (such as pressure factors or mitigation measures).
  • Indicators or a set of questions may provide a framework which helps to identify the relevant environmental information. They also help to condense environmental data to understandable information.

Identification of existing sources of information

The third step is to identify existing sources of information for the required information about the environmental situation. Whether this search is successful depends on the particular plan or programme concerned and on the monitoring systems existing for the environmental factors concerned. Two main sources of environmental information which may be useful for monitoring the significant environmental effects of plans and programmes are presented in the following section.

a) Data at project level

The first data source contains environmental data about the projects for which the plan sets the framework. Environmental data at project level are generated and collected at different stages of the project realisation. During the licensing phase of a project, information about its likely effects on the environment is collected for the purpose of the project EIA (although the data gathered in an EIA procedure are also prognostic they are usually more detailed than those used at the planning level) or other development consent procedures. During the construction and the operation phase the project is subject to inspections in order to make sure that the conditions set out in the development consent are observed in practice. Further, the IPPC Directive requires the establishment of a pollution emissions register covering emissions from a large number of industrial installations.[25]

Data at project level in most cases cover pressure factors such as emissions and also to some extent environmental effects. These data can help to compare the prediction of environmental effects and the achievement of environmental targets on the planning level with the real effects resulting from the implementation of the plan or programme.

Usually information at project level is collected by other authorities than those in charge of monitoring of plans and programmes. It must therefore be ensured that the data are made available to the monitoring authority if the monitoring system is to depend on project-related data. Also it has to be taken into account, that information at project level is mainly focused on small-scaled environmental effects while the SEA is often performed for large-scale plans or programmes. Therefore the information from the project level has to be processed, aggregated and summarised in order to use it for the monitoring of a plan or programme.

b) General environmental monitoring

The second and wide-spread source of environmental information consists in general environmental monitoring systems including statistics providing environmental data without being specifically related to plans, programmes or projects. Although these data show changes in the environment and thus environmental effects they only allow conclusions limited as to the impact resulting from the implementation of the plan or programme (as the cause-effect link is difficult to establish). However, these data can be used to find out whether environmental objectives and targets included in a plan or programme have been achieved. They also may give an indication about the efficiency of measures undertaken or foreseen to achieve these targets. Such sources of general environmental monitoring schemes, statistics and investigations can be found in all Member States and are to a large extent also required by EC legislation (e.g. monitoring according to Articles 5 and 8 of the Water Framework Directive 2000/60/EC or Directive on Ozone in ambient air 2002/3/EC).[26]

  • Sources of environmental information can be found at project level (e.g. information gathered in EIA procedures or emissions registers established on the basis of the IPPC Directive).
  • Environmental information at project level addresses pressure factors and environmental effects. Information at project level needs to be aggregated and summarized when it is used for the planning level.
  • General environmental monitoring systems provide environmental data detecting changes in the environment. These data help to verify the achievement of environmental objectives and targets but they allow only to a limited extent the changes in the environment to be attributed to the implementation of the plan or programme.
  • EC legislation contains various provisions requiring the collection of environmental data which may be useful for the purpose of Article 10.

Filling the gaps

The fourth step is to fill the gaps that are found when comparing the existing sources of information to the needs following from Article 10 for the specific plan or programme. In some cases the information may be sufficient to fulfil the requirements of Article 10, but it may be necessary to provide for a continuous exchange of information between the authorities collecting the information and the authority responsible for monitoring. In other cases existing monitoring systems may have to be enlarged by including additional aspects or measuring points. Yet it should be stressed that monitoring according to Article 10 has a limited purpose, i.e. to identify shortcomings of the environmental assessment, and that it is not a free-standing scientific exercise. This always has to be borne in mind when thinking about enlarging existing monitoring systems or installing new ones.

Procedural integration of monitoring into the planning system

The fifth step is to integrate monitoring into the planning system. As said above, monitoring does not have to be a separate step in the planning procedure, but it can be part of the regular planning system. A good point in the administrative process to integrate the monitoring required by the SEA Directive appears to be the regular revision of an existing plan or programme. If there is no such regular revision, time and frequency for monitoring the effects of the plan or programme should be laid down, either in a general rule or in the context of each individual environmental report.

In any case some procedural arrangements have to be made to ensure that the monitoring system runs effectively. It has to be determined which authority (or other body) is responsible for the different tasks of monitoring, comprising the collection of environmental information, processing the environmental information and their evaluation. Further, it is important that the relevant information is submitted to the respective authority in an appropriate form (e.g. environmental data should be explained and put in an understandable document when presented to a decision-making body).

When setting up monitoring arrangements it should be noted that monitoring does not end with the collection of environmental information but includes also their evaluation.

  • Monitoring can be integrated in the planning system.
  • Efficient monitoring demands a determination of the responsible authority/ies and the time and frequency of monitoring measures.
  • Monitoring arrangements should also include the evaluation of the environmental information.

Remedial action

Environmental information received through monitoring can be of assistance when considering appropriate remedial action in the framework of national legislation. Article 10, however, does not lay down an obligation to undertake remedial action. The following section therefore contains only general reflections about remedial action.

It may be useful to determine criteria which trigger an examination of remedial action. Existing legislation in some Member States contains already general provisions requiring a revision of the plan if this is necessary to ensure the intended development (e.g. to ensure a well balanced urban development).

Remedial action can be taken on different levels. On the planning level, the decision on the adoption of the plan or programme can be reversed and a new plan or programme can be adopted or the existing plan or programme one can be modified. If the legal system of the Member States so allows, remedial action could also be taken on the implementation level. This could in particular mean that those statements in the plan or programme which have been proved incorrect or which were based on incorrect assumptions are no longer considered as a framework for the development consent of single projects.

Remedial action on the planning level could also be combined with such action on the implementation level. This would mean that the plan or programme is modified on the basis of the new information on its effects on the environment. In order to avoid developments which might occur while the (old) plan or programme is still in force and which might contravene the envisaged modification of the plan or programme, development consent procedures for projects could be postponed or the decision on projects could be taken without referring to the plan or programme if the respective national legal systems so allows.

  • It may be useful to determine criteria which trigger the consideration of remedial action.
  • Remedial action can be undertaken on planning level and implementation level.

 

Appendix II - Members of the Working Group

  • Ursula Platzer, Federal Ministry of Agriculture, Forestry, Environment and Water Management, Austria
  • Andreas Sommer, Provincial Government of Salzburg, Department of Environmental Protection, Austria
  • Ulla-Riitta Soveri, Ministry of the Environment, Finland
  • Otmar Lell and Astrid Langenberg, Federal Ministry for the Environment, Nature Conservation and Nuclear Safety, Germany
  • Matthias Roder, Bavarian Ministry of Regional Development and Environmental Affairs, Germany
  • Mari Van Dreumel, Ministry of Housing, Spatial Planning and the Environment, Netherlands
  • Sten Jerdenius, Ministry of the Environment, Sweden
  • David Aspinwall and Phil Weatherby, Office of the Deputy Prime Minister, UK
  • Lieselotte Feldmann, European Commission, Directorate-General Environment
  • Antti Maunu, European Commission, Directorate-General Environment

Appendix III - Bibliography

Andreas Sommer, 'The Assessment of the Significance of Environmental Effects. Procedure and Criteria for Screening in Strategic Environmental Assessments', the Austrian Federal Ministry of Agriculture, Forestry, Environment and Water Management, 2002

Royal Haskoning, 'Quality assurance strategic environmental assessment'. Commissioned by the Netherlands Ministry of Housing, Spatial planning and the Environment, 2002

Environmental Resource Management, 'Public participation and stakeholders' involvement in the SEA process: an overview of available techniques and methodologies', commissioned by the Netherlands Ministry of Housing, Spatial planning and the Environment, 2002

European Union Network for the Implementation and Enforcement of Environment Law (IMPEL). IMPEL PROJECT: Implementation of Article 10 of the EA Directive 2001/42/EC

Jonathan Robinson, 'Anticipating the effect of Strategic Environmental Assessment', at Planning law: Analysing Reform, Europe and Caselaw, White Paper Conference, London, 21 March 2002.

 

Notes

[23] A current model for the causal chain is the DPSIR scheme (driving forces-pressure-state-impact-response).

[24] For more details see final report of the IMPEL project.

[25] A comprehensive overview of EC legislation requiring the collection of project-related
environmental data is to be found in the final report of the IMPEL project.

[26] A more detailed overview of relevant EC legislation is given in the final report of the IMPEL project.


9. RELATION WITH OTHER EC LEGISLATION

Top