EIA/IC/S/3 Armenia
![]() |
Party (State) of origin | Armenia |
Affected Party (State) | Azerbaijan |
Activity (project) | Submission by Azerbaijan having concerns about Armenia’s compliance with its obligations under the Convention, with respect to the planned construction of a nuclear power station in Metsamor, Armenia (5 May 2011) |
Draft decision IS/1b on compliance by Armenia with its obligations under the Convention in respect of a nuclear power plant in Metsamor (ECE/MP.EIA/2019/3) | ENG | FRE | RUS |
---|
Information on matters considered by the Committee
Submission by Azerbaijan having concerns about Armenia’s compliance with its obligations under the Convention (EIA/IC/S/3)
Submission by Azerbaijan having concerns about Armenia’s compliance with its obligations under the Convention, with respect to the planned construction of a nuclear power station in Metsamor, Armenia (5 May 2011).
At its twenty-first session (20 June 2011), the Implementation Committee took note of the submission by Azerbaijan (ECE/MP.EIA/IC/2011/4, para.12).
The Committee considered the matter at its twenty-second (5-7 September 2011, ECE./MP.EIA/IC/2011/6, para. 16-21), twenty-third (5-7 December 2011, ECE/MP.EIA/IC/2011/8, paras. 12-15), twenty-fourth (20-23 March 2012, ECE/MP.EIA/IC/2012/2, paras. 11-13) and twenty-fifth sessions (11-13 September 2012, ECE/MP.EIA/IC/2012/4, paras. 7 and 8).
Before finalizing its findings and recommendations the Implementation Committee sent its draft to the Parties concerned and invited them to submit their comments or representations according to para. 9 of the Structure and Functions of the Implementation Committee and Procedures for Review of Compliance (appendix to Decicion III/2). Both Parties sent their comments and representatios to the Committee on due time.
At its twenty-sixth session (26-28 November 2012) the Committee finalized its findings and recommendations taking into account representations and comments received from the two Parties concerned (ECE/MP.EIA/IC/2012/6, paras. 11-15 and Annex I).
At its sixth session (Geneva, 2-5 June 2014), the Meeting of the Parties requested the Committee to follow up and, as appropriate, monitor the steps in the transboundary EIA procedure in relation to the planned construction of the Metsamor NPP (decision VI/2, paras. 45–46). At its thirty-second session (Geneva, 9-11 December 2014), the Committee took note of the information from Armenia that the Government, through decision 511-A of 19 May 2014, had approved its new energy programme, which among other projects, envisaged that the construction of the new block of the NPP would only start in 2018. Armenia also informed the Committee that that the decision for the planned construction of the NPP was no longer valid, the activities based on that decision were suspended and that there was no transboundary EIA procedure relating to that project. Thus the Committee decided that there was no longer a ground to follow up on the decision VI/2, paras. 45–46. It decided to recommend to the Meeting of the Parties to close the case and to encourage Armenia to ensure that any projects carried out in accordance with energy-related programmes, including nuclear activities, be in compliance with the Convention.
The Committee also observed that the Programme of the Government of 19 May 2014 seemed to set the framework for future activities in the energy field. Therefore, as Armenia was a Party to the Protocol on SEA, the Committee initiated an information-gathering procedure on Protocol matters (SEA/IC/INFO/2) to establish whether the Government programme in question should have been a subject to an SEA
For the outcomes of the Committee’s deliberations since the seventh session of the Meeting of the Parties (Minsk, 13-16 June 2017), please see the Committee’s report on its forty-second session.
Document Title | ENG | FRE | RUS |
---|---|---|---|
Submission by Azerbaijan |
|
| |
Reply by Armenia |
|
| |
Report of the Implementation Committee on its twenty-first session (ECE/MP.EIA/IC/2011/4) | ENG | FRE | RUS |
Report of the Implementation Committee on its twenty-second session (ECE/MP.EIA/IC/2011/6) | ENG | FRE | RUS |
Report of the Implementation Committee on its twenty-third session (ECE/MP.EIA/IC/2011/8) | ENG | FRE | RUS |
Report of the Implementation Committee on its twenty-fourth session (ECE/MP.EIA/IC/2012/2) | ENG | FRE | RUS |
Letter from the Chair of the Committee to Azerbaijan (25.04.2012) | ENG | ||
Letter from the Chair of the Committee to Armenia (25.04.2012) | ENG | ||
Comments and representations by Azerbaijan (15.08.2012) | ENG | ||
Comments and representations by Armenia (14.08.2012) | ENG | ||
Report of the Implementation Committee on its twenty-fifth session (ECE/MP.EIA/IC/2012/4) Corrigendum to the Report of the Implementation Committee on its twenty-fifth session (only for the English version) (ECE/MP.EIA/IC/2012/4/ Corr.1) | ENG | FRE | RUS |
Report of the Implementation Committee on its twenty-sixth session (ECE/MP.EIA/IC/2012/6) | ENG | FRE | RUS |
Report of the Meeting of the Parties on its sixth session (decision VI/2 on review of compliance) | ENG | FRE | RUS |
Follow up to decision VI/2 | |||
Letter from the Minister of Nature Protection to the UNECE Executive Secretary (1 August 2014) regarding the follow-up to decision VI/2 in relation to S/4 (Metsamor NPP) | |||
Letter from the UNECE Executive Secretary (20 August 2014) | ENG | ||
31st session of the Committee | |||
Letter to Armenia on CI/1 and S/3 (21.09.2014) | ENG | ||
Letter from Armenia on CI/1 and S/3 (19.11.2014) | ENG | ||
32nd session of the Committee | |||
Letter to Armenia on CI/1 and S/3 (after IC32, sent 24.12.2014) | ENG | ||
Report of the activities of the Implementation Committee to the Meeting of the Parties on its seventh session (paras 27-29) ECE/MP.EIA/2017/4−ECE/MP.EIA/SEA/2017/4 | ENG | FRA | RUS |
Draft decision on the review of compliance with the Convention (ECE/MP.EIA/2017/8, paras 45-47) | ENG | ||
---|---|---|---|
Report of the Meeting of the Parties to the Convention on its seventh session and of the Meeting of the Parties to the Convention serving as the Meeting of the Parties to the Protocol on its third session (ECE/MP.EIA/23 - ECE/MP.EIA/SEA/7, para 27) | ENG | FRE | RUS |
Report of the thirty-ninth session of the Implementation Committee (ECE/MP.EIA/IC/2017/4, para 31) | ENG | FRE | RUS |
Report of the forty-first session of the Implementation Committee (ECE/MP.EIA/IC/2018/2, para 14) | ENG | FRE | RUS |
Report of the forty-second session of the Implementation Committee (ECE/MP.EIA/IC/2018/4, paras 11-13) Advance copy | ENG | ||
Draft decision IS/1b on compliance by Armenia with its obligations ubder the Convention in respect of a nuclear power plant in Metsamor (ECE/MP.EIA/2019/3) | ENG | FRE | RUS |